Critical path method (CPM)

The critical path method identifies the longest sequence of dependent activities in a project: it sets the project's minimum duration and the activities with no slack.

Definition

For each activity, the early and late dates are calculated; the difference is the slack (or float). Activities with zero slack form the critical path: any delay on one of them delays the whole.

When to use it

  • To plan a project or an action plan
  • To know where to concentrate resources
  • To assess the effect of a delay

How to build it

  1. List the activities. With their estimated duration.
  2. Define the dependencies. Which activities must finish before others can start.
  3. Calculate. Forward and backward passes, slack, critical sequence.
  4. Monitor. Recalculate with every change: the critical path evolves.

Common mistakes

  • Calculating once at the start and then forgetting it
  • Ignoring implicit dependencies
  • Optimistic durations

Example

Opening a branch: lease → renovation → equipment, with hiring in parallel; renovation is critical, hiring has 15 days of slack.

Your strategy deserves to be executed.

Run your strategic diagnosis in minutes, turn it into objectives and follow their execution every day.

30 days free · no credit card · in English, French, Spanish, Portuguese, German and 4 Nordic languages