Definition
For each activity, the early and late dates are calculated; the difference is the slack (or float). Activities with zero slack form the critical path: any delay on one of them delays the whole.
When to use it
- To plan a project or an action plan
- To know where to concentrate resources
- To assess the effect of a delay
How to build it
- List the activities. With their estimated duration.
- Define the dependencies. Which activities must finish before others can start.
- Calculate. Forward and backward passes, slack, critical sequence.
- Monitor. Recalculate with every change: the critical path evolves.
Common mistakes
- Calculating once at the start and then forgetting it
- Ignoring implicit dependencies
- Optimistic durations
Example
Opening a branch: lease → renovation → equipment, with hiring in parallel; renovation is critical, hiring has 15 days of slack.