# Critical path method (CPM)

> The critical path method identifies the longest sequence of dependent activities in a project: it sets the project's minimum duration and the activities with no slack.

Source: https://manstra.net/en/methods/critical-path-method


## Definition

For each activity, the early and late dates are calculated; the difference is the slack (or float). Activities with zero slack form the critical path: any delay on one of them delays the whole.

## When to use it

- To plan a project or an action plan
- To know where to concentrate resources
- To assess the effect of a delay

## How to build it

1. **List the activities** — With their estimated duration.
2. **Define the dependencies** — Which activities must finish before others can start.
3. **Calculate** — Forward and backward passes, slack, critical sequence.
4. **Monitor** — Recalculate with every change: the critical path evolves.

## Common mistakes

- Calculating once at the start and then forgetting it
- Ignoring implicit dependencies
- Optimistic durations

## Example

Opening a branch: lease → renovation → equipment, with hiring in parallel; renovation is critical, hiring has 15 days of slack.

## With Manstra

Manstra recalculates each plan's critical path on every change, ranks everyone's priorities and projects delays onto objectives.